5afda5f7b205f474a342e856 fde9bea52ae5092f870cd81eb2cd3e49292f500145e19cafda7ab4e50a149f41 web

Location

National Grid’s first major overhead line project to start construction under a DCO

Project summary

  • Fisher German has been re-appointed by National Grid to continue working on the Richborough Connection Project, a new 400kV overhead line between Richborough and Canterbury
  • The project will include the construction of 20km of electricity pylons and required substation infrastructure. We have assisted National Grid with planning
  • The Development Consent Order (DCO) for the project is a significant landmark, as this is National Grid’s first major overhead line project to start under a DCO

Solution

  • The instruction will cover the construction phase, including the delivery of land rights along with related modifications to the local electricity distribution network
  • Once built, the line will connect Nemo Link – undersea electricity cables between Herdersbrug in Belgium and Ramsgate in the UK – to National Grid’s high voltage electricity network
  • It is intended to integrate the UK into a single European electricity market via interconnectors, allowing the trading of power via undersea cables, ensuring the UK has a safe, reliable and secure electricity supply
  • We used our expertise to conduct the consultation process, secure land access, arrange agreements with landowners and represent the project in planning hearings

Benefits

  • We were working to tight time constraints, but National Grid was granted a DCO by the Department for Business, Energy and Industrial Strategy in August 2017. We were pleased with this result and being able to contribute to securing this major DCO

More Case Studies

Top